Yamama Cement Plant

    When Yamama Cement Factory was completed with a clinker production line with a capacity of 10,000 tons / day, it was a facility registered as the highest capacity of klinker produced in a single preheater in the world.

    Preheater tower of the plant was the highest of its kind with a height of +205 meters.

    Handar has completed complete mechanical equipment assembly, structural steel work, all heavy lifting operations, refractory works, including complete field fabrication of the preheater structure of the facility.
    Location:
    Riadh - Saudi Arabia
    Client:
    Yamama Saudi Cement Company
    Project Scope:
    Preheather Tower...
    Technical Data: 7.924 Ton
    Start-Finish Date:
    01.05.2005 - 30.10.2006